Latest Works Progress
Works Progress of the Tung Chung East Section
| Tung Chung East Station | |
| Completed: ✔ Installation of two pedestrian bridges connecting station entrances |
In Progress: ● Structural works of the station concourse and roof |
| Major Track Diversion Works | |
| Completed: ✔ Installation and energisation of the overhead line for the new Hong Kong-bound track section |
In Progress: ● Adjusting the existing Tung Chung-bound Tung Chung Line track for connection to the new section ● Installation of trackside equipment for the new railway section |

▲ Structural works of the station concourse and roof

▲ Overhead line for the new Hong Kong-bound track section
Tung Chung West Section Progress
| Tung Chung West Station | |
| Completed: ✔ Construction of the station top slab |
In Progress: ● Construction of the station concourse slab ● Station excavation ● Structural works for Exit and Entrance B and the South Ventilation Building |
| Tunnel Construction | |
| Completed: ✔ Tunnel boring towards Tung Chung West Station ✔ U-turn operation of Tunnel Boring Machine |
In Progress: ● Tunnel boring towards Tung Chung Station ● Construction of TBM retrieval shaft ● Structural, Architectural Builder’s Works and Finishes, and Building Services works for the emergency access and plant room on the Shun Tung Road hillside |

▲ Construction of the station concourse slab

▲ Tunnel towards Tung Chung West Station