Latest Works Progress
Works Progress of the Tung Chung East Section
| Tung Chung East Station | |
| Completed: ✔ Main station structural works ✔ Installation of platform screen doors ✔ Installation of external claddings for the footbridge |
In Progress: ● Interior fitting-out, and electrical and mechanical (E&M) works |
| Major Track Diversion Works | |
| Completed: ✔ Dynamic train test of the new Hong Kong-bound track section ✔ Track slewing of the existing Tung Chung-bound track |
In Progress: ● Trial operations on the new Hong Kong-bound track section |

▲ Main station structure

▲ Interior fitting-out, and electrical and mechanical (E&M) works

▲ Dynamic train test of the new Hong Kong-bound track section
Tung Chung West Section Progress
| Tung Chung West Station | |
| Completed: ✔ Station bulk excavation works ✔ Concourse slab construction |
In Progress: ● Internal structural works at concourse level ● Construction of the platform level base slab ● Structural works for aboveground station entrances and ventilation buildings |
| Tunnel Construction | |
| Completed: ✔ Tunnel excavation works |
In Progress: ● Structural, Architectural Builder’s Works and Finishes, and Building Services works for the emergency access and plant room on the Shun Tung Road hillside |

▲ Internal structural works at concourse level

▲ Structural works for aboveground station entrances and ventilation buildings

▲ Tunnel breakthrough