Latest Works Progress
Works Progress of the Tung Chung East Section
Completed: | In progress: |
✔ Substructure works of Tung Chung East station and underground pipe-laying works ✔ First turnout installation ✔ Site formation and advance works for track laying |
Construction of the station platform and concourse |
Construction of two integrated entrances and exits to the north of the station | |
Modification and extension of noise barrier | |
Major track diversion works, including: o Track slewing works on the existing Tung Chung Line o Modification of overhead cables and other railway facilities o Laying of new tracks to the west of Tung Chung East Station |
▲ Site formation and advance works for track laying
▲ Construction of the station platform and concourse
▲ Newly built noise barriers
Works Progress of the Tung Chung West Section
Completed: | In progress: |
✔ Construction of diaphragm wall for Tung Chung West Station | Foundation and ground floor structure works of the new station |
✔ Construction of temporary noise enclosures and launching shaft at the Shun Tung Road works site. | Transportation and assembly of tunnel boring machine components, as well as tunnel construction related works |
✔ Erection of tower crane and slurry treatment facilities at the works site on the Shun Tung Road hillside | Building monitoring and condition surveys in Ma Wan Chung Village |
▲ Transportation and assembly of tunnel boring machine components
▲ Building monitoring in Ma Wan Chung Village